Welcome to our site!

We will be utilizing this site to share updates as we continue to build the new Josiah Quincy Upper School. 

Weekly Updates

Week of 6/28/24

  • Tile work at portals.

  • Electrical and fire alarm work ongoing.

  • Mechanical balancing in building.

  • Auditorium millwork ongoing.

  • Auditorium theatre equipment install.

  • Alt. PE flooring install.

  • Painting stairs and punch list.

  • Ceiling tile install for ATC ceilings.

  • Exterior excavation and foundations for landscaping.

  • Rooftop landscaping ongoing.

  • Stretch fabric panel install.

  • Bleachers assemble/install. 

Week of 6/24/24

  • Tile work ongoing level 1 and 2, and portals.

  • Electrical and fire alarm work ongoing.

  • Mechanical balancing in building.

  • Auditorium millwork.

  • Auditorium theatre equipment install.

  • Window frame and glass install ongoing.

  • Resinous flooring on level 2.5.

  • Alt. PE flooring preparation.

  • Painting level 1-6 and stairs.

  • Ceiling tile install for ATC ceilings.

  • Exterior excavation and foundations for landscaping.

  • Rooftop landscaping ongoing.

Week of 6/17/24

  • Tile work ongoing level 1 and 2, and portals.

  • Electrical and fire alarm work ongoing.

  • Mechanical startup concluding.

  • Auditorium/stage millwork.

  • Window frame and glass install ongoing.

  • Resinous flooring on stair C.

  • Stage flooring install.

  • Painting level 1-6 and stairs.

  • Ceiling grid framing for ATC ceilings.

  • Exterior excavation and foundations for landscaping.

  • Rooftop landscaping ongoing.

Week of 6/9/24

  • Interior drywall and taping on L1, L2 and stairways.

  • Tile work ongoing level 1 and 2, and portals.

  • Electrical and fire alarm work ongoing.

  • Mechanical startup concluding.

  • Auditorium/stage millwork.

  • Window frame and glass install ongoing.

  • Resinous flooring on level 1 and 2.

  • Gymnasium floor graphics and vinyl graphics.

  • Painting level 1-6 and stairs.

  • Ceiling grid framing for ATC ceilings.

  • Exterior excavation and foundations for landscaping.

  • Rooftop landscaping ongoing.

Week of 5/20/24

  • Interior drywall and taping on L1, L2 and stairways.

  • Tile work ongoing level 1 and 2.

  • Electrical and fire alarm work ongoing.

  • Mechanical startup proceeding.

  • Auditorium/stage taping.

  • Stage subfloor install.

  • Window frame and glass install ongoing.

  • 2nd floor resilient floor install.

  • Resinous flooring on level 1 and 2.

  • Gymnasium wood floor install.

  • Painting level 1-6 and stairs.

  • Ceiling grid framing for ATC ceilings.

  • Exterior excavation and foundations for landscaping.

  • Rooftop landscaping ongoing.

Week of 5/13/24

  • Interior drywall and taping on L1, L2 and stairways.

  • Tile work ongoing level 1 and 2.

  • Electrical and fire alarm work ongoing.

  • Mechanical startup proceeding.

  • Auditorium/stage drywall and taping.

  • Stage floor prep.

  • Window frame and glass install ongoing.

  • 6th and 3rd floor resilient floor install.

  • Resinous flooring on level 1 and 2.

  • Gymnasium wood floor install.

  • Painting level 1-6 and stairs.

  • Ceiling grid framing for ATC ceilings.

  • Exterior excavation and foundations for landscaping.

  • Rooftop landscaping ongoing.

Week of 5/6/24

  • Interior drywall and taping on L1, L2, and stairways.

  • Tile work ongoing level 1 and 2.

  • Electrical and fire alarm work ongoing.

  • Mechanical startup proceeding.

  • Auditorium/stage drywall and taping.

  • Black box floor preparation and subfloor install.

  • Window frame and glass install ongoing.

  • 5th floor resilient floor install.

  • Resinous flooring ongoing.

  • Gymnasium wood floor install.

  • Painting level 1-6 and stairs.

  • Ceiling grid framing for ATC ceilings.

  • Exterior excavation and foundations for landscaping.

  • Rooftop landscaping ongoing.

Week of 4/29/24

  • Interior drywall and taping on L1, L2, and stairs.

  • Tile work ongoing level 1 and 2.

  • MEP work ongoing on level 1 through 7

  • Waterproofing exterior wall. 

  • Auditorium/stage drywall and taping.

  • Stage rigging system and pipe grid install.

  • Roof work on level 7 high roof.

  • Window frame and glass install ongoing.

  • 4th floor resilient floor install.

  • Resinous flooring ongoing.

  • Gymnasium wood floor install.

  • Black box room floor install.

  • Painting level 1-6.

  • Ceiling grid framing for ATC ceilings.

  • Exterior excavation and foundations for landscaping.

  • Rooftop landscaping mobilize.

Week of 4/22/24

  • Interior drywall and taping on L1, L2.

  • Tile work ongoing level 2.

  • MEP work ongoing on level 1 through 7

  • Waterproofing exterior wall. 

  • Auditorium/stage framing and drywall.

  • Ceiling grid framing for ATC ceilings.

  • Roof work on level 7 high roof.

  • Window frame and glass install ongoing.

  • Brick install at hoist leave out. 

  • 6th and 3rd floor floor leveling and resilient floor.

  • Resinous flooring on level 1 and 2.

  • Gymnasium wood floor subfloor install.

  • Prep work for black box flooring.

  • Painting level 1-6.

  • Exterior excavation and foundations for landscaping.

Week of 4/8/24

  • Interior drywall and taping on L1, L2, L2.5.

  • Tile work ongoing level 1-6 and stair D.

  • MEP work ongoing on level 1 through 7.

  • First floor MEP work below isolation ceiling.

  • Waterproofing exterior wall.

  • Auditorium/stage framing and drywall.

  • Roof work on level 7 high roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall at auditorium exterior.

  • Brick install at hoist leave out. 

  • 5/6th floor floor leveling and resilient floor.

  • Resinous flooring on level 4.

  • Painting level 1-6.

  • Exterior excavation for landscaping.

Week of 4/1/24

  • Interior drywall and taping on L1, L2, L2.5.

  • Tile work ongoing level 1-6 and stair D.

  • MEP work ongoing on level 1 through 7.

  • First floor MEP work below isolation ceiling.

  • Waterproofing exterior wall.

  • Auditorium/stage framing and drywall.

  • Roof work on level 7 high roof and level 2.5 east roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall at auditorium exterior.

  • Brick install at hoist leave out. 

  • 4/5th floor floor leveling and resilient floor.

  • Floor leveling and floor install at kitchen.

  • Resinous flooring on level 4.

  • Painting level 1-6.

  • Exterior excavation for landscaping work mobilize.

Week of 3/25/24

  • Interior drywall and taping on L1, L2, L2.5.

  • Tile work ongoing level 2.5-6 and stair D.

  • MEP work ongoing on level 1 through 7.

  • First floor MEP work below isolation ceiling.

  • Waterproofing exterior wall.

  • Auditorium/stage framing and drywall, ceiling cloud taping, painting, and lighting.

  • Elevator erection on going. 2 cars in use.

  • Roof work on level 7 high roof and level 2.5 east roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall at gymnasium bump out.

  • Exterior sheathing at hoist leave out.

  • Gym isolation slab.

  • 4/5th floor floor leveling and resilient floor.

  • Resinous flooring on level 4.

  • Painting level 3-6.

  • Permanent power switch over.

Week of 3/11/24

  • Interior drywall and taping on L1, L2, L2.5.

  • Tile work ongoing level 2.5-6 and stair C.

  • MEP work ongoing on level 1 through 7.

  • First floor MEP work below isolation ceiling.

  • Waterproofing exterior wall.

  • Auditorium/stage framing and drywall, ceiling cloud taping, painting, and lighting.

  • Elevator erection on going. 2 cars in use.

  • Roof work on level 7 high roof and level 2.5 east roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall at gymnasium bump out.

  • Exterior sheathing at hoist leave out.

  • Gym equipment installation.

  • 4th floor floor leveling and resilient floor.

  • Resinous flooring on level 4.

  • Painting in gym and level 3-6.

  • Preparation for gym concrete isolation slab.

 

Week of 3/4/24

  • Wall framing L1 and 2. Interior drywall and taping on L1, L2, L2.5.

  • Tile work ongoing level 2.5-6 and stair C.

  • MEP work ongoing on level 1 through 7.

  • First floor MEP work below isolation ceiling.

  • Waterproofing exterior wall.

  • Auditorium/stage framing and drywall, ceiling cloud framing and lighting.

  • Elevator erection on going. 2 cars in use.

  • Roof work on level 7 high roof and level 2.5 east roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall at gymnasium bump out.

  • Removal of scaffolding at exterior western wall. 

  • Exterior sheathing at hoist leave out.

  • Gym equipment installation.

  • 4th floor floor leveling and resilient floor.

  • Resinous flooring on level 4.

  • Painting in gym and level 3-6.

Week of 2/26/24

  • Wall framing L1 and 2. Interior drywall and taping on L2.5, L3, L4, L5, L6.

  • Tile work ongoing level 2.5-6 and stair C.

  • MEP work ongoing on level 1 through 7.

  • First floor MEP work below isolation ceiling.

  • Waterproofing exterior wall.

  • Auditorium framing and drywall, ceiling cloud framing and lighting.

  • Elevator erection on going. 2 cars in use.

  • Roof work on level 7 high roof and level 2.5 east roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall at gymnasium bump out.

  • Remove scaffolding in stage and at exterior western wall. 

  • Exterior sheathing at hoist leave out.

  • Gym equipment installation.

  • 4th floor floor leveling and resilient floor.

  • Resinous flooring mobilize and start on level 4.

Week of 2/19/24

  • Wall framing L1 and 2. Interior drywall and taping on L2.5, L3, L4, L5, L6.

  • Tile work ongoing level 2.5-6.

  • MEP work ongoing on level 1 through 7.

  • First floor MEP work below isolation ceiling.

  • Waterproofing exterior wall.

  • Auditorium framing and drywall, ceiling cloud framing and lighting.

  • Elevator erection on going. 2 cars in use.

  • Roof work on level 7 high roof and level 2.5 east roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall at gymnasium bump out.

  • Scaffolding erection at hoist leave out area.

  • Relieving angles at hoist leave out.

  • Gym equipment installation.

Week of 2/5/24

  • Wall framing L1 and 2. Interior drywall and taping on L2.5, L3, L4, L5, L6.

  • Tile work ongoing level 2.5-6.

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Auditorium framing and drywall, ceiling cloud framing.

  • Elevator erection on going. 1 car in use.

  • First floor MEP work below isolation ceiling.

  • Roof work on level 7 high roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall at gymnasium bump out.

  • Scaffolding erection at hoist leave out area.

Week of 1/29/24

  • Wall framing L1 through L2.5. Interior drywall and taping on L2.5, L3, L4, L5, L6.

  • Painting/priming in the gymnasium.

  • Tile work ongoing level 3-6.

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Auditorium framing and drywall.

  • Install catwalk steel railings.

  • Elevator erection on going. 1 car in use.

  • Hoist take down.

  • First floor MEP work below isolation ceiling.

  • Roof work on level 2.5 and high roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall at gymnasium bump out.

Week of 1/22/24

  • Wall framing L1 through L2.5. Interior drywall and taping on L2.5, L3, L4, L5, L6.

  • Painting/priming in the gymnasium.

  • Tile work ongoing level 3-6.

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Auditorium framing and drywall.

  • Install catwalk steel railings.

  • Elevator erection on going.

  • First floor MEP work below isolation ceiling.

  • Roof work on level 2.5 and high roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall at gymnasium bump out.

  • Stair A erection completion and concrete.

Week of 1/15/24

  • Wall framing L1 through L2.5. Interior drywall and taping on L2.5, L3, L4, L5 L6.

  • Painting/priming in the gymnasium.

  • Tile work ongoing level 3-6.

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Auditorium drywall.

  • Install catwalk steel railings.

  • Elevator erection on going.

  • First floor MEP work below isolation ceiling.

  • Roof work on level 2.5 and high roof.

  • Window frame and glass install ongoing.

  • Tower crane concrete pad demolition.

Week of 1/8/24

  • Wall framing L1 through L2.5. Interior drywall and taping on L2.5, L3, L4, L5 L6.

  • Painting/priming on level 2.5 and 6.

  • Tile work ongoing level 3-6.

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Auditorium in-wall rough.

  • Elevator erection on going.

  • First floor MEP work below isolation ceiling.

  • Roof work on level 2.5 and high roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall on roof.

Week of 12/25/23

  • Wall framing L1 through L2.5. Interior drywall and taping on L2.5, L3, L6.

  • Painting/priming on level 6 and auditorium open ceiling.

  • Scaffolding takedown where brick complete.

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Auditorium framing and drywall.

  • Elevator erection on going.

  • First floor isolation ceiling install.

  • Roof work on level 2.5 and high roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall on roof.

Week of 12/11/23

  • Wall framing L1 through L2.5. Interior drywall and taping on L2.5, L5, L6.

  • Painting/priming on level 4-6 and misc.

  • Tile work ongoing level 4-6.

  • Scaffolding takedown where brick complete.

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Mason demobilization.

  • Auditorium open steel MEP Rough.

  • Auditorium framing and drywall.

  • Elevator erection on going.

  • First floor isolation ceiling install.

  • Roof work on level 2.5 and high roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall on roof.

Week of 12/04/23

  • Wall framing L1 through L2.5. Interior drywall and taping on L2.5, L5, L6.

  • Painting/priming on level 3-5.

  • Tile work ongoing on level 5/

  • Scaffolding takedown where brick complete.

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Auditorium open steel MEP Rough.

  • Auditorium framing and drywall.

  • Elevator erection on going.

  • First floor isolation ceiling install.

  • Roof work on level 2.5 and high roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall on roof.

Week of 11/27/23

  • Wall framing L1 through L2.5 and L6. Interior drywall and taping on L5.

  • Painting/priming on level 4 and 5.

  • Tile work ongoing on level 4 and 5.

  • Scaffolding erection around building. Scaffolding takedown where brick complete.

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall at gymnasium.

  • Mason installing brick at exterior wall.

  • Auditorium open steel SOFP.

  • Elevator erection on going.

  • First floor isolation ceiling install.

  • Roof work on level 2.5 and high roof.

  • Window frame and glass install ongoing.

  • Exterior wall metal panel wall on roof.

Week of 11/20/23

  • Wall framing L1 through L6. Interior drywall and taping on L5.

  • Painting/priming on level 4. 

  • Tile work on level 4.

  • Scaffolding erection around building. Scaffolding takedown where brick complete on Pine Street. 

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Auditorium open steel SOFP.

  • Elevator erection on going.

  • First floor isolation ceiling install.

  • Roof work at level 3.

  • Window frame and glass install ongoing.

Week of 11/13/23

  • Wall framing L1 through L6. Interior drywall and taping on L5.

  • Painting/priming on level 4. 

  • Tile work ongoing on level 4.

  • Scaffolding erection around building. Scaffolding takedown where brick complete on Pine Street. 

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Auditorium hangers for ceiling clouds and auditorium MEP systems.

  • Elevator erection on going.

  • First floor isolation ceiling install.

  • Window frame and glass install ongoing.

Week of 10/30/23

  • Wall framing L1 through L6. Interior drywall and taping on L4.

  • Scaffolding erection around building. Scaffolding takedown where brick complete on Pine Street. 

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Auditorium scaffolded dance floor move from L3 to catwalk/L2.5

  • Elevator erection on going.

  • First floor isolation ceiling install.

Week of 10/16/23

  • Wall framing L1 through L6. Interior drywall starting on L4.

  • Scaffolding erection around building. Scaffolding takedown where brick complete on Pine Street. 

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Auditorium catwalk stair erection.

  • Elevator mobilization.

  • Polish concrete on ground level on going.

Week of 9/25/23

  • Wall framing L1 through L6. Interior drywall starting on L4.

  • Scaffolding erection around building.

  • MEP work ongoing on level 1 through 7.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Continued erection of stair D.

  • Elevator shaft wall and ductwork ongoing.

  • Polish concrete on ground level on going.

Week of 9/18/23

  • Wall framing L1 through L6.

  • Scaffolding erection around building.

  • MEP work ongoing on level 1 through 6.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Continued erection of stair D.

  • Elevator shaft wall and ductwork ongoing.

  • Polish concrete on ground level on going.

Week of 9/4/23

  • Exterior wall studs and sheathing.

  • Wall framing L1 through L6.

  • Scaffolding erection around building.

  • MEP work ongoing on level 1 through 6.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Continued erection of stair D.

  • Elevator shaft wall and ductwork ongoing

  • Painting at Eversource vault room and in auditorium.

  • Start of polish concrete on ground level.

Week of 8/21/23

  • Exterior wall studs and sheathing.

  • Wall framing L1 through L6.

  • Scaffolding erection around building.

  • MEP work ongoing on level 1 through 6.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Continued erection of stair C, stair C concrete.

  • Elevator shaft wall and ductwork ongoing

Week of 8/14/23

  • Exterior wall studs and sheathing.

  • Scaffolding erection around building.

  • MEP work ongoing on level 1 through 6.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Continued erection of stair C, stair C concrete.

  • Elevator shaft wall and ductwork ongoing.

Week of 7/24/23

  • Continued early walls.

  • Exterior wall studs and sheathing.

  • Scaffolding erection around building.

  • MEP work ongoing on level 1 through 6.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Continued erection of stair C

  • Spray on fireproofing at auditorium.

Week of 7/24/23

  • Continued early walls.

  • Exterior wall studs and sheathing.

  • Auditorium concrete.

  • Scaffolding erection around building.

  • MEP work ongoing on level 1 through 5.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Continued erection of stair C

 

JQUS Project Tower Crane Removal

  • Friday 7/14 8PM - Sunday 7/16 11 PM

  • Work will take place for 24 hours/day

  • Marginal Road will be closed to vehicular traffic

  • Washington Street, Harrison Ave, Pine Street and all sidewalls will remain open

 

Week of 7/3/23

  • Continued early walls.

  • Exterior wall studs and sheathing.

  • Auditorium concrete.

  • Scaffolding erection around building.

  • MEP work ongoing on level 1 through 5.

  • Waterproofing exterior wall.

  • Mason installing brick at exterior wall.

  • Continued erection of stair C.

Work and Events

Tower Crane Removal

 

Friday July 14th at 8 PM to Sunday July 16th at 11PM. Work will be taking place 24 hours/day. Marginal Road will be closed to vehicular traffic. Washington Street, Harrison Avenue, Pine Street and all sidewalks will remain open.

Saturday Steel Erection

 

For more information please see the Project Updates page.

Crawler Crane Assembly

 

September 24th & 25th - Saturday and Sunday 6AM-5PM.

Assemble crawler crane inside site along Marginal Road. Increased trucking/ deliveries during working hours.​

For more information please see the Project Updates page.

Water Shutdown - 900 Washington and 888 Oak Terrace

 

Temporary shutdown of 16" water main in Washington Street for tie-in of new water service.

For more information please see the Project Updates page.

Tower Crane Assembly

 

Roadways will remain open, access may be limited along the ally of Pine St. for public safety. 

  • Off Hours Work: Friday 8/12 6PM-12AM

  • Off Hours Work: Saturday 8/13 12AM-12AM

  • Off Hours Work: Sunday 8/14 12AM-7PM

For more information please see the Project Updates page.

Marginal Way Closure

 (From Harrison Ave to Washington St)
 

This work has been delayed - more information to come 

Washington Street Lane Closures 6/27/22 to 7/29/22

Washington Street Utilities
 

H-Pile Driving Advisory
 

During the week of 02/28 and 03/07 mobilization of 2 cranes will take place to prepare for pile driving operations. 

  • Mobilize Pie Driving Equipment 03/04 - 03/08

  • Test Pile Program 03/08 - 03/18

  • Production Piles moving East to West 03/18 - May 2022

For more information please see the Project Updates page.

Saturday 2/19/22 Work
 

For more information please see the Project Updates page.

Community Meeting 11/30/21
 

For more information please see the News & Events page.

The meeting is now ONLY VIRTUAL (zoom only).

JQUS Meeting Flyer 11-30-21.jpg

Parking Notice
 

Parking Screen Shot Feb 2022.jpg

For more information please see the Project Updates page.

JQUS Breaks Ground
On Tuesday, June 15, 2022, the Josiah Quincy Upper School in Boston’s Chinatown celebrated its ground breaking ceremony. The project is significant to the JQUS community and the City of Boston, and this project has been in planning for over a decade. The new school will offer future students a 21st century learning environment with facilities for challenging, research based programming.  Currently, students at the existing JQUS are distributed between two buildings: one on Arlington Street that was built in 1912, and a pre cast concrete annex building on Washington Street that was built in the 1990’s. These two facilities house over 500 students in grades 6-12.