Welcome to our site!
We will be utilizing this site to share updates as we continue to build the new Josiah Quincy Upper School.
Weekly Updates
Week of 12/04/23
-
Wall framing L1 through L2.5. Interior drywall and taping on L2.5, L5, L6.
-
Painting/priming on level 3-5.
-
Scaffolding takedown where brick complete.
-
MEP work ongoing on level 1 through 7.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Auditorium open steel MEP Rough.
-
Auditorium framing and drywall.
-
Elevator erection on going.
-
First floor isolation ceiling install.
-
Roof work on level 2.5 and high roof.
-
Window frame and glass install ongoing.
-
Exterior wall metal panel wall on roof.
Week of 11/27/23
-
Wall framing L1 through L2.5 and L6. Interior drywall and taping on L5.
-
Painting/priming on level 4 and 5.
-
Scaffolding erection around building. Scaffolding takedown where brick complete.
-
MEP work ongoing on level 1 through 7.
-
Waterproofing exterior wall at gymnasium.
-
Mason installing brick at exterior wall.
-
Auditorium open steel SOFP.
-
Elevator erection on going.
-
First floor isolation ceiling install.
-
Roof work on level 2.5 and high roof.
-
Window frame and glass install ongoing.
-
Exterior wall metal panel wall on roof.
Week of 11/20/23
-
Wall framing L1 through L6. Interior drywall and taping on L5.
-
Painting/priming on level 4.
-
Scaffolding erection around building. Scaffolding takedown where brick complete on Pine Street.
-
MEP work ongoing on level 1 through 7.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Auditorium open steel SOFP.
-
Elevator erection on going.
-
First floor isolation ceiling install.
-
Roof work at level 3.
-
Window frame and glass install ongoing.
Week of 11/13/23
-
Wall framing L1 through L6. Interior drywall and taping on L5.
-
Painting/priming on level 4.
-
Scaffolding erection around building. Scaffolding takedown where brick complete on Pine Street.
-
MEP work ongoing on level 1 through 7.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Auditorium hangers for ceiling clouds and auditorium MEP systems.
-
Elevator erection on going.
-
First floor isolation ceiling install.
-
Window frame and glass install ongoing.
Week of 10/30/23
-
Wall framing L1 through L6. Interior drywall and taping on L4.
-
Scaffolding erection around building. Scaffolding takedown where brick complete on Pine Street.
-
MEP work ongoing on level 1 through 7.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Auditorium scaffolded dance floor move from L3 to catwalk/L2.5
-
Elevator erection on going.
-
First floor isolation ceiling install.
Week of 10/16/23
-
Wall framing L1 through L6. Interior drywall starting on L4.
-
Scaffolding erection around building. Scaffolding takedown where brick complete on Pine Street.
-
MEP work ongoing on level 1 through 7.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Auditorium catwalk stair erection.
-
Elevator mobilization.
-
Polish concrete on ground level on going.
Week of 9/25/23
-
Wall framing L1 through L6. Interior drywall starting on L4.
-
Scaffolding erection around building.
-
MEP work ongoing on level 1 through 7.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Continued erection of stair D.
-
Elevator shaft wall and ductwork ongoing.
-
Polish concrete on ground level on going.
Week of 9/18/23
-
Wall framing L1 through L6.
-
Scaffolding erection around building.
-
MEP work ongoing on level 1 through 6.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Continued erection of stair D.
-
Elevator shaft wall and ductwork ongoing.
-
Polish concrete on ground level on going.
Week of 9/4/23
-
Exterior wall studs and sheathing.
-
Wall framing L1 through L6.
-
Scaffolding erection around building.
-
MEP work ongoing on level 1 through 6.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Continued erection of stair D.
-
Elevator shaft wall and ductwork ongoing
-
Painting at Eversource vault room and in auditorium.
-
Start of polish concrete on ground level.
Week of 8/21/23
-
Exterior wall studs and sheathing.
-
Wall framing L1 through L6.
-
Scaffolding erection around building.
-
MEP work ongoing on level 1 through 6.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Continued erection of stair C, stair C concrete.
-
Elevator shaft wall and ductwork ongoing
Week of 8/14/23
-
Exterior wall studs and sheathing.
-
Scaffolding erection around building.
-
MEP work ongoing on level 1 through 6.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Continued erection of stair C, stair C concrete.
-
Elevator shaft wall and ductwork ongoing.
Week of 7/24/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Scaffolding erection around building.
-
MEP work ongoing on level 1 through 6.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Continued erection of stair C
-
Spray on fireproofing at auditorium.
Week of 7/24/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Auditorium concrete.
-
Scaffolding erection around building.
-
MEP work ongoing on level 1 through 5.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Continued erection of stair C
JQUS Project Tower Crane Removal
-
Friday 7/14 8PM - Sunday 7/16 11 PM
-
Work will take place for 24 hours/day
-
Marginal Road will be closed to vehicular traffic
-
Washington Street, Harrison Ave, Pine Street and all sidewalls will remain open
Week of 7/3/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Auditorium concrete.
-
Scaffolding erection around building.
-
MEP work ongoing on level 1 through 5.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
Continued erection of stair C.
Week of 6/26/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Auditorium concrete.
-
Scaffolding erection around building.
-
MEP work ongoing on level 1 through 5.
-
Waterproofing exterior wall.
-
Mason installing brick at exterior wall.
-
MEP Equipment delivery for high roof.
-
Continued erection of stair C
Week of 6/19/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Auditorium concrete.
-
Scaffolding erection around building and over auditorium.
-
MEP work ongoing on level 1 through 4.
-
Waterproofing exterior wall.
-
Mason installing concrete block and brick
-
MEP Equipment delivery for 2.5 roof.
-
Stair C mobilization and erection
Week of 6/5/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Auditorium concrete.
-
Scaffolding erection around building and over auditorium.
-
MEP work ongoing on level 2, 2.5, and 3.
-
Waterproofing exterior wall.
-
Mason installing concrete block and brick
-
MEP Equipment on roof
Week of 5/15/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Auditorium concrete pour #1.
-
Scaffolding erection around building and over auditorium.
-
MEP work ongoing on level 2, 2.5, and 3.
-
Waterproofing exterior wall.
-
Mason installing concrete block and brick
-
Roofing on level 7.
-
Demolish temporary footings.
Week of 5/8/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Level 6 concrete.
-
Scaffolding erection around building.
-
MEP work ongoing on level 2, 2.5, and 3.
-
Waterproofing exterior wall.
-
Mason installing concrete block and brick
-
Roofing mobilization.
-
Excavate and demolish temporary footings.
Week of 5/1/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Rebar on level 6.
-
Concrete pours on levels 4, 5, and 6.
-
Scaffolding erection around building.
-
MEP work ongoing on level 2 and 2.5
-
Waterproofing exterior wall
-
Mason installing concrete block and brick
Week of 4/17/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Rebar on level 4.
-
Level 1 concrete pour #8 and #9.
-
Scaffolding erection around building.
-
MEP work ongoing on level 2 and 2.5.
-
De-shoring process continues.
-
Mason start on eastern exterior wall.
Week of 4/10/23
-
Continued early walls.
-
Exterior wall studs and sheathing.
-
Rebar on level 1.
-
Level 1 concrete pour #7.
-
Scaffolding erection around building.
-
MEP work ongoing on level 2 and 2.5.
-
De-shoring process starts.
-
Mobilization of mason.
Week of 4/3/23
-
Continued early walls.
-
Rebar on level 1.
-
Level 1 concrete pour #6.
-
Scaffolding erection around building.
-
MEP work ongoing on level 2 and 2.5.
-
Welding throughout building.
Week of 3/13/2023
-
Continued early walls.
-
Rebar at level 7 and level 1.
-
Level 7 concrete pour #1.
-
Level 1 concrete pour #2.
-
Installation of drain line in Marginal Road.
-
Scaffolding erection around building.
-
MEP work ongoing on level 2 and 2.5.
Week of 3/6/2023
-
Continued early walls.
-
Rebar at level 7 and level 1.
-
Level 7 concrete pour #1.
-
Level 1 concrete pour #1.
-
Scaffolding erection around building.
-
MEP work ongoing on level 2 and 2.5.
Week of 2/27/2023
-
Continued early walls.
-
Scaffolding erection around building.
-
MEP work ongoing on level 2 and 2.5.
-
Rebar for slab on grade, first slab on grade pour.
Week of 2/20/2023
-
Continued early walls.
-
Exterior wall at gym
-
MEP work ongoing on level 2 and 2.5.
-
Rebar for slab on grade.
Week of 2/13/2023
-
AHU delivery and placement on level 2.5
-
Turn over of floors 7 and 5.
-
Build wall at AHU on level 2.5.
-
Start early walls.
-
MEP work ongoing level 2.
-
Exterior wall at gym.
Week of 1/23/2023
-
Structural steel and deck erection on level 7 and roof.
-
Level 4 MEP and rebar.
-
Temporary hoist assembly.
-
Metal framing level 2 clips layout.
-
Spray On Fireproofing Level 2.5 and 2.
-
Underground plumbing
-
Building scaffolding in SE corner.
Week of 1/16/2023
-
Structural steel and deck erection on level 7 and roof.
-
Level 4 MEP and rebar.
-
Temporary hoist assembly.
-
Metal framing level 2 clips layout.
-
Spray On Fireproofing Level 2.5 and 2.
Week of 1/09/2023
-
Structural steel and deck erection on level 7.
-
Level 4 partial turn-over.
-
Temporary hoist erection starts.
-
Metal framing level 2 clips layout
-
Spray On Fireproofing Level 2.5 and 2.
Week of 12/26/2022
-
Structural steel erection on level 6 and 7.
-
Erect structural steel for mock-up.
-
Crawler crane demobilization.
-
Level 2.5 rebar on remaining areas.
-
Pour #3 on Level 2.5.
Week of 12/5/2022
-
Structural steel erection on level 5 and 6.
-
Level 3 rebar and MEP work on turned over deck.
-
Pour #3 on Level 3.
-
Steel Topping
Week of 11/28/2022
-
Structural steel erection on level 5 and 6.
-
Level 3 rebar and MEP work on turned over deck.
-
Pour #2 on Level 3.
Week of 11/21/2022
-
Structural steel erection on level 5.
-
Auditorium truss installation/ level 3 steel erection.
-
Level 3 rebar and MEP work on turned over deck.
-
Pour #1 on Level 3.
-
Form and pour mockup pad at 152 Arlington Street (current JQUS).
Week of 11/14/2022
-
Structural steel erection on level 5.
-
Auditorium truss installation
-
Level 3 rebar and MEP work on turned over deck.
Week of 11/07/2022
-
Structural steel erection on level 5.
-
Level 2.5 MEP on tuned over deck. Continued temporary lighting install.
-
Slab on Metal Deck prep and install rebar.
Week of 10/31/2022
-
Structural steel erection on level 4.
-
Level 2.5 MEP on tuned over deck. Continued temporary lighting install.
-
Slab on Metal Deck prep and install rebar.
-
Saturday steel erection. See work and events/project updates for more information.
Week of 10/24/2022
-
Structural steel erection on level 4.
-
Level 2 MEP on tuned over deck. Continued temporary lighting install.
-
Slab on Metal Deck prep and install rebar.
Week of 10/16/2022
-
Structural steel erection on level 4, gym trusses
-
Level 2 MEP on tuned over deck, temporary lighting install.
Week of 10/10/2022
-
Structural steel erection on level 4, bolt and detail level 3.
-
Level 2 MEP on tuned over deck.
Week of 10/03/2022
-
Steel Erection Level 3, Leve 2.5 auditorium and gym with trusses.
Week of 9/19/2022
-
Steel Erection Level 2.5
-
Paving over temporary drain line work on Harrison Ave and in site.
-
Move barriers in preparation for crawler crane.
-
Saturday/Sunday 9/24-25 assembly of crawler crane. See work and events section.
Week of 9/12/2022
-
Steel Erection Level 2
-
Irrigation Line Connection and Backfill
-
Pour concrete ductbank for tele-data and main electrical ductbank
Week of 9/12/2022
-
Steel Erection Level 2
-
Irrigation Line Connection and Backfill
-
Pour concrete ductbank for tele-data and main electrical ductbank
Week of 8/8/2022
-
Backfilling of Infiltration System
-
Backfilling of Site
-
Weekend: Tower Crane Assembly - See Work and Events
Week of 8/1/2022
-
Infiltration System Pipe Install
-
Backfilling of Infiltration System
-
Utilities work onsite
Week of 7/18/2022
-
Backfilling Pile Caps and Grade Beams
-
Excavation of Infiltration System
-
Utilities work in Washington Street
Week of 6/13/2022
-
Concrete Pile Caps and Grade Beams
-
Backfilling Pile Caps and Grade Beams
-
Work on tower crane foundation
Week of 5/23/2022
-
Concrete Pile Caps and Grade Beams
-
Backfilling Pile Caps and Grade Beams
Week of 5/2/2022
-
Concrete Pile Caps and Grade Beams
-
Excavation of site for concrete work.
Week of 4/11/2022
-
H-pile completion.
-
Excavation of site.
-
Mobilization for concrete work.
Week of 4/4/2022
-
H-pile production - West Side
-
Start excavation of east site of site
Week of 3/21/2022
-
H-pile test program
-
H-pile production - East
Week of 3/07/2022
-
H-pile mobilization
-
H-pile test pile program
-
Mini pile installation
Week of 2/28/2022
-
Mini Pile Installation
-
Pre-excavation for piles
-
H-pile mobilization
Week of 2/10/2022
-
Mini Pile Installation
-
Demolition/Abatement of BCEC foundation
-
Saturday 2/18 work, 115KV pipe removal and BCEC slab demolition.
Week of 1/17/2022
-
Pre-excavation for piles
-
Support of Excavation at Pines Street
-
Test pile on job site
Week of 1/10/2022
-
Remediation of contaminated soils
-
Cut and cap 6" water line at Washington Street sidewalk
-
Begin installing support of excavation by Pine Street
Week of 12/20/2021
-
Continued demolition of the JQUS modular building mat slab
-
Test pits for unknown utilities
Week of 12/5/2021
-
Continued demolition of the JQUS modular building
-
Begin demolition of mat slab.
Week of 11/28/2021
-
Temporary shutdown of Pine Street for water access for demolition.
-
Continued demolition of BCEC
-
Begin demolition of JQUS modular building.
Week of 11/21/2021
-
Temporary shutdown of Pine Street for water access for demolition.
-
Demolition of BCEC
-
Installation of new fire hydrant on Marginal Road
Week of 10/18/2021
-
Temporary shutdown of Pine street for excavation
-
Parking restrictions on Washington Street will be enforced starting 10/19.
-
New striping, signage, fencing, and signals at Harrison Ave and Marginal Road intersection, Marginal Road and Washington Street intersection, Washington Street and Pine Street intersection, and Pine street and Harrison Ave intersection.
-
Installation of jersey barriers and site fence
Work and Events
Tower Crane Removal
Friday July 14th at 8 PM to Sunday July 16th at 11PM. Work will be taking place 24 hours/day. Marginal Road will be closed to vehicular traffic. Washington Street, Harrison Avenue, Pine Street and all sidewalks will remain open.
Tower Crane Assembly
Roadways will remain open, access may be limited along the ally of Pine St. for public safety.
-
Off Hours Work: Friday 8/12 6PM-12AM
-
Off Hours Work: Saturday 8/13 12AM-12AM
-
Off Hours Work: Sunday 8/14 12AM-7PM
For more information please see the Project Updates page.
Marginal Way Closure
(From Harrison Ave to Washington St)
This work has been delayed - more information to come
Washington Street Lane Closures 6/27/22 to 7/29/22
Washington Street Utilities
H-Pile Driving Advisory
During the week of 02/28 and 03/07 mobilization of 2 cranes will take place to prepare for pile driving operations.
-
Mobilize Pie Driving Equipment 03/04 - 03/08
-
Test Pile Program 03/08 - 03/18
-
Production Piles moving East to West 03/18 - May 2022
For more information please see the Project Updates page.
Saturday 2/19/22 Work
For more information please see the Project Updates page.
Community Meeting 11/30/21
For more information please see the News & Events page.
The meeting is now ONLY VIRTUAL (zoom only).

JQUS Breaks Ground
On Tuesday, June 15, 2022, the Josiah Quincy Upper School in Boston’s Chinatown celebrated its ground breaking ceremony. The project is significant to the JQUS community and the City of Boston, and this project has been in planning for over a decade. The new school will offer future students a 21st century learning environment with facilities for challenging, research based programming. Currently, students at the existing JQUS are distributed between two buildings: one on Arlington Street that was built in 1912, and a pre cast concrete annex building on Washington Street that was built in the 1990’s. These two facilities house over 500 students in grades 6-12.